基于熵权分析法的油库建设方案综合评价研究

范影1石铤燚1王莹莹2佟震3吴玉国1   

  1. 1.辽宁石油化工大学 石油天然气工程学院,辽宁 抚顺 113001; 2.中盈绿能机电股份有限公司,辽宁 大连 116003; 3.中冶沈勘秦皇岛工程设计研究总院有限公司,河北 秦皇岛 066004
  • 收稿日期:2020-03-05 修回日期:2020-04-19 出版日期:2021-04-30 发布日期:2021-05-20
  • 作者简介:范影(1978-),女,硕士,讲师,从事建筑节能等方面的研究;E-mail:89558454@qq.com。
  • 基金资助:
    辽宁省教育厅其他项目“石油化工企业火灾防控关键技术研究”(2018-510-00)。

Comprehensive Evaluation of Oil Depot Construction Scheme Based on Entropy Weight Analysis

Fan Ying1Shi Tingyi1Wang Yingying2Tong Zhen3Wu Yuguo1   

  1. 1.College of Petroleum Engineering,Liaoning Petrochemical University,Fushun Liaoning 113001,China; 2.Zhongying Green Energy Electromechanical Co. Ltd.,Dalian Liaoning 116003,China; 3.Shen Kan Qinghuangdao General Engineering Design &Reserch Institute Corporation,MCC,Qinhuangdao Hebei 066004,China
  • Received:2020-03-05 Revised:2020-04-19 Published:2021-04-30 Online:2021-05-20

摘要: 建筑施工标准化和文明化不仅是施工现场的最低要求,而且是新时代建筑领域的创新点,关系着社会经济发展及国家现代化进程。以某油库的招、投标信息为依托,选取4种不同施工方案,构建了标准化施工管理评价指标体系,采用归一化处理法确定各指标权重;在此基础上,通过熵权法与综合评价法构建了标准化施工方案评价体系,对4种施工方案(M1—M4)进行了评价。结果表明,方案标准化、文明化程度排序为M3>M4>M1>M2;一级指标权重排序为环境>安全>节能>成本>质量>进度。其中,环境因素权重占比最大,约为0.193,项目进度因素的权重占比最小,约为0.128。因此,在油库建设施工过程中重点应放在施工环境和安全建设等方面,走绿色、标准化、可持续的发展道路。

关键词: 综合评价法, 未确知测度, 油库建设, 标准化

Abstract: Construction standardization and civilization are not only the minimum requirements of the construction site, but also the innovation of the construction field in the new era, which are related to the social and economic development and the process of national modernization.Based on the recruitment and bidding information of an oil depot and taking four different construction schemes as the basic data, a standardized construction management evaluation index system was firstly constructed. On this basis, the standardized construction scheme evaluation system was constructed by entropy weight method and comprehensive evaluation method. The results show that the degree of standardization and civilization of the four schemes is ranked as M3>M4>M1>M2. The first⁃level index weight ranking is environment>safety>energy saving>cost>quality>progress. Among them, the weight proportion of environment factor is the largest, about 0.193, and the weight proportion of project progress factor is the smallest, about 0.128. Therefore, during the construction of oil depot, the emphasis should be placed on construction environment and safety construction, and the road of green, standardized and sustainable development should be taken.

Key words: Comprehensive evaluation method, Unascertained measure, Oil depo, Standardized

引用本文

范影, 石铤燚, 王莹莹, 佟震, 吴玉国. 基于熵权分析法的油库建设方案综合评价研究[J]. 辽宁石油化工大学学报, 2021, 41(2): 51-58.

Fan Ying, Shi Tingyi, Wang Yingying, Tong Zhen, Wu Yuguo. Comprehensive Evaluation of Oil Depot Construction Scheme Based on Entropy Weight Analysis[J]. Journal of Liaoning Petrochemical University, 2021, 41(2): 51-58.

使用本文

0
    /   /   推荐

导出引用管理器 EndNote|Ris|BibTeX

链接本文: https://journal.lnpu.edu.cn/CN/10.3969/j.issn.1672-6952.2021.02.010

               https://journal.lnpu.edu.cn/CN/Y2021/V41/I2/51